Westshore Terminals Railcar Dumper

November 2008

 

Brymark was selected by Metso Minerals to install a new railcar dumper at Westshore Terminals that would accommodate modern aluminum body railcars. Brymark removed the existing railcar dumper, completed the necessary modifications to the remaining equipment, and installed a new dumper provided by Metso Minerals.

 

OWNER

Westshore Terminals Ltd.

LOCATION

Roberts Bank, Delta, B.C.

HIGHLIGHTS

  • Roof removal and other prep/finishing work completed while dumper was in operation.
  • Brymark adjusted construction schedule "on the fly" to take advantage of unexpected dumper downtime between railcar deliveries.
  • Tight shutdown schedule maintained during removal of old dumper and installation of new dumper.
  • No recordable injuries.

 

SECTOR

Material Handling

DURATION

2 Months

COMPLETION

September 2008

MANPOWER

10

SUBCONTRACTS

GWIL Crane

Westpac Electric

Aluma Scaffold Systems

CONSULTANTS

Metso Minerals

CONTACT

John Bears or Tim Danard




On August 15th, Brymark Installations, in conjunction with Sterling Crane, completed a two crane, 310,000lb lift at Westshore Terminals in Delta

August 18, 2009

On March 2nd, a crew of carpenters and labourers broke ground for our long awaited office expansion.

March 18, 2009

Brymark Installations Group Inc. is pleased to announce its successful re-qualification for the CSABC Health & Safety Certificate of Recognition

February 25, 2009

Brymark, in conjunction with Gwil Crane, Aluma Scaffold Systems, and Westpac Electric, recently completed the installation of a new railcar dumper at the Westshore Terminal in Delta, BC.

November 2008